October 2009

3rd October

Just Lynda and I again this week. Lynda now has the sleeper on 12 lengths painted plus two out of the three points we need. I managed to get the third point retimbered so that is now ready for painting. There are a few lengths that are going to need all new sleepers but I think we may just leave those till last as we may not need them.

 

10th October

Another short handed day. A successful one none the less. Managed to get the hard-core in for about 70ft. and have got the base gravel in and rolled. just need to get some ballast and start track laying.

Compacted and ready for the track

Compacted and ready for the track

cr43

Adding the Gravel

Adding the Gravel

cr46

Into the Station area

Into the Station area